About The Project
Point of Contact
Richard Slade
Project Value
£85,000
Programme
4 Weeks
Location
250 South Oak Way – Reading
Scope of Work:
- Installation of new Dado trunking for Power
- LCM’s for suspending lighting
- Feature lighting and panel lighting
- Distribution equipment,
- Data cabinets
- Cabling
- Containment and RJ45 Outlets
Challenges:
- Other floors were still in use by other companies.
- Project had a completion date that was not negotiable, so materials had to be ordered in advance to reduce lead times
Results:
- New offices for ISG
- Energy efficient lighting
- Sufficient data and power points for desk working.
- Cleaner and more presentable offices for ISG
- More space for meetings